Tuesday, May 23 – Tuesday, June 6

Crews will be repairing Knox’s parking lot beginning Tuesday May 23. This will require closing sections of the lot per the following schedule:

  • May 23 & 24 – South entrance and lower lot will be closed
  • May 24 – Upper east lot and connector driveway will be closed
  • May 25 – Upper middle and west lots will be closed, and possibly the North entrance
  • May 25 – End of day, both entrances and all lots will be re-opened for use May 26 – 29
  • May 30 & 31 – Upper lot work resumes, North entrance closed
  • June 1 – All pavement repairs to be completed
  • June 5 & 6 – Pavement will be seal coated and stripes painted

If bad weather interrupts work, we expect seal coating and stripes will be completed no later than June 12 & 13.

Please contact Carl Combs with any questions.